What is the earliest that activity d can begin if activity a takes 3 days, activity b takes 5 days, and activity c takes 7 days?

Business · High School · Thu Feb 04 2021

Answered on

To determine the earliest start time for activity D, we need to know the dependencies between the activities. We must know if activities A, B, and C are dependent on each other, and if activity D depends on any or all of these previous activities.

Assuming activity D can only begin once activities A, B, and C have all been completed, the earliest start time for activity D would be after the longest of these three activities is completed.

If activities A, B, and C can run concurrently (at the same time), then you would look at the activity that takes the longest, which is activity C at 7 days. Therefore, the earliest activity D can begin is after 7 days.

If, however, activities A, B, and C must be completed sequentially (one after the other), you would add up the time for all three activities: 3 days for A, 5 days for B, and 7 days for C, which totals 15 days. In this case, activity D can begin on day 16.

Extra: In project management, the timing of activities is often represented in a Gantt chart or a network diagram. Dependencies between tasks are crucial when planning a project. There are typically four types of dependencies:

1. Finish-to-Start (FS): Task B cannot start until Task A has finished. This is the most common type of dependency. 2. Start-to-Start (SS): Task B cannot start until Task A has started. 3. Finish-to-Finish (FF): Task B cannot finish until Task A has finished. 4. Start-to-Finish (SF): Task B cannot finish until Task A has started.

Using a Critical Path Method (CPM) analysis could also help to determine the longest stretch of dependent activities and the earliest and latest that each activity can start and finish without making a project longer. This would then identify the minimum project duration and the "critical path," or the sequence of activities that determine the length of the project.

Related Questions