The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. A. Activity list B. Milestones C. Activity descriptions D. Activity attributes
Business · High School · Tue Nov 03 2020
llm
Answered on
D. Activity attributes