During a Sprint, the features are broken down into smaller elements and put on theSprint Backlog. Which one of the following statements best describes these smallerelements? a. Activities estimated in duration scrum b. Tasks estimated in hours (effort) c. Tasks estimated in duration d. Activities estimated in hours (effort)

Business · College · Thu Feb 04 2021

Answered on

b. Tasks estimated in hours (effort)

In Scrum, during the Sprint Planning meeting, the selected features or user stories are broken down into more manageable units called tasks. These tasks are estimated in hours (effort) rather than in duration. This is because estimating tasks in terms of effort allows the team to consider complexity, uncertainty, and the amount of work required to complete a task, rather than how many days or weeks it would take to complete it. This estimation helps the team to manage their Sprint Backlog more effectively, ensuring that they can meet the goals of the Sprint within the set timeframe.